Six chips
The flights take days. The factories take months.
Field marks. Each chip spends 6 to 20 days moving between stops, and 36 to 231 days in factories.
Look-alike. Lead time is a different clock. The L298N takes about 45 to 98 days to make and ship, and its factory lead time is 52 weeks. Most of that is waiting for a slot, not making.
Range. Only Espressif publishes its own times: about 3 months for wafers, 4 to 6 weeks to package and test, and 3 to 4 weeks to build modules. The other times are industry figures, company figures or our estimates.
Habitat. One documented route per chip, wafer start to shelf. The lead time is DigiKey’s and Mouser’s on 26 Oct 2026.